A planning application submitted to Staffordshire Moorlands District Council (SMDC) on 17th May 2016 confirms:
- A wooden rollercoaster structure with a silent magnetic lift system
- Themed enclosed sound tunnels, noise screens and tunnels
- The first drop will be enclosed in a sound tunnel
- Comparative noise assessments referred to in the plans confirm the manufacturer to be GCI
- Construction will begin in September 2016 with a forecast Spring 2018 opening
- Some existing buildings around the former Flume site will be demolished
- A 140 second pre-show for 50 guests
- The ride footprint will not encroach into the nearby woodland
Updated plans submitted in August 2016 show that the former substantial combined maintenance building, station and shop will now be smaller separate buildings (August 2016 L, May 2016 R):
Changes to the area include a new games unit and food kiosk, while the former Mexican Cantina and Flume photo booth will be demolished. Buildings are expected to have thatched effect roof tiles and weathered timber effects, many being single storey.
Ride layout as shown within the plans:
The plans indicate separate onload and offload areas along with a manned baggage store such as those featured on Th13teen and The Smiler.
What else do the plans say?
A more in-depth look at the plans shows us track elevations, air time hills and the locations we can expect to see theming elements. The plans don't tell us exactly how high the lift hill will be, instead indicating the ride's high and low points in comparison to sea level.
Rumours, speculation and high hopes
As with all plans released, fans of the park will develop theories and speculation based on both what the documents say, and also hopes for the final product. Current speculation for SW8 involves inversions, a short dark ride section, and a launched lift hill. Remember, there's no confirmation of these points yet!
Dark ride section?
(Referencing the May 2016 plans) Dark ride sections have appeared on a number of coasters around the world, for example Blue Fire at Europa Park and also the wooden coaster Mammut at Tripsdrill. The May 2016 plans contained a large station/maintenance building and the track layout within the building shows a few turns which could accommodate a short on-ride show.
With the latest August 2016 revised plans, sections of the track are now outdoors and it is therefore unlikely we will see a dark ride section. But we do know that guests can expect a lengthy pre-show and have seen evidence of theming around the rest of the ride, including a giant theming element on the site of the Flume's old station.
Inversions?
Speculation began when the plans appeared to possible show inverting track, with a support structure similar to inverting wooden rollercoasters currently in operation.
As construction started during the 2017 season however and the plans were translated into real life it soon became clear that the coaster would not include inversions.
Launched lift?
Although not confirmed to be a launch, the plans do confirm that SW8 will feature a silent magnetic lift. Magnetic LSM launches are used across the world on a variety of rollercoasters to produce a launch, for example on the wooden coaster Lightning Rod at Dollywood. Whether the magnetic lift will be fast enough to constitute a launch, it is not yet known.
But what will the theme be?
While early banners for SW8 used familiar Mutiny Bay branding, as construction got under way in 2017 this was swapped out for new teasers that focused on the wooden element of the ride.
Much of the theme speculation centred around a trademark application for Wicker Man, which was rumoured to be related to the new coaster. Adding fuel to the speculation, the 2017 park map listed SW8 as belonging to Gloomy Wood, which backs the ride receiving a more horror based theme.
As of January 2018 the park finally confirmed the ride's name as Wicker Man, promising an immersive experience fusing fire into their new wooden coaster.
Early Plans
In these early plans from April 2016, the ride may be quite familiar when compared to the final product but look closely at the 3D Overview of the ride and you'll be able to spot two Wicker Men theming elements. These plans were produced shortly before planning permission was applied for, when the team were still deciding where the effigy would be placed. The 3D overview therefore shows the two potential locations being considered.
Construction
Demolition of The Flume took place during the closed season at the end of 2016 and by January 2017 groundwork had begun on the groundwork for the new coaster.
By the start of the 2017 season work had begun on the foundations and the first wood was spotted on site on during May. From there construction progressed quickly and the lift hill topped out with a flag ceremony on 7th July 2017.
Work has continued to progress quickly throughout the site over summer, in August focus shifted to the giant themeing element being built inside a tarpaulin clad tower, roughly on the site of the old Flume station. At the same time Alton Towers Marketing machine kicked into action with mysterious symbols appearing around the site and on the attractions marketing.
- March 2016
- 2nd April 2017
- 14th April 2017
- 23rd June 2017
- 25th June 2017
- 6th July 2017
- 9th July 2017
- 15th July 2017
- 16th July 2017
- 26th July 2017
- 3rd August 2017
- 11th August 2017
- 22nd August 2017
- 29th August 2017
- 2nd September 2017
- 3rd September 2017
- 11th September 2017
- 14th September 2017
- 23rd September 2017
- 2nd October 2017
- 5th October 2017
- 16th October 2017
- 28th October 2017
- 3rd December 2017
- 17th December 2017
Marketing
The park first revealed that The Flume's site would be home to the next Secret Weapon during the 2016 season when the fences surrounding the defunct ride received a series of announcement banners using the familiar Mutiny Bay branding. However at the dawn of the 2017 season the ride started to be distanced from its pirate neighbours with advertising which focused much more heavily on the coaster's wooden elements. Indeed the season's park map labelled the new development as being part of Gloomy Wood.
Marketing for SW8 kicked into full steam during August 2017 as strange carvings began to appear in the fencing around the ride. It soon became apparent that three of the symbols represented SW8, whilst another mysterious phrase was deciphered as 'Be Chosen'. The on-site decals were accompanied by a new page on the Alton Towers site that started to unveil the story surrounding the ride.
The updates to the Alton Towers site also saw two new videos unveiled, one of which focused on the history of the Secret Weapon ride programme whilst the second was a teaser about SW8. The teaser video revealed more of the mysterious runes that are central to the new ride's marketing, leading to enthusiasts across the country to start work on creating their very own SW8 rune alphabet.
'Be Chosen' is also the tag line for the new Scarefest maze in 2017, which will take place in the Mutiny Bay Courtyard across the way from SW8. The Welcoming - Be Chosen will focus on the back story of the coaster, echoing a similar link between The Sanctuary and The Smiler during the SW7 development. The maze focuses on a mysterious group of wood dwellers that shun technology and come together at Halloween to celebrate in their own unique manner and is sure to give us a taste of what we can expect from the coaster's theme.
In early October the park unveiled the logo for the ride, which matched up with the 'Graphic Representation' that accompanied the trademark application for Wicker Man that fuelled so much speculation over the summer. It was not until January however that the park confirmed the name, when the promotional artwork for the new ride was released, including elements produced by artist Kyle Lambert.
What is a Secret Weapon?
In the early 90's when Alton Towers was taken over by the Tussauds Group, John Wardley was tasked with designing a major roller coaster to help in the process of transforming the park from a collection of fairground rides in the woods, to a modern theme park.
His initial designs involved the use of a prototype roller coaster from Arrow Dynamics (who also built the Big One at Blackpool and Vampire at Chessington World of Adventures). The prototype roller coaster looked a bit like a missile so the theme was pitched around a "Secret Weapon". John Wardley made two different designs for this ride, labelled SW1 and SW2.
Eventually it was decided the ride wasn't what the park wanted and instead they worked with B&M to create Nemesis, and although the theme for this ride changed, the project was still titled a secret weapon and became SW3.
Since then every major roller coaster with the exception of Spinball Whizzer and Rita have been labeled "SW" during the design and construction phase until the name is chosen and announced. The next major roller coaster installation will be SW8!
What are the existing Secret Weapons?
- SW1 - Arrow Dynamics prototype, never built
- SW2 - Arrow Dynamics prototype, never built
- SW3 - B&M inverted coaster - Nemesis (1994)
- SW4 - B&M dive coaster - Oblivion (1998)
- SW5 - B&M flying coaster - Air (2002)
- SW6 - Intamin drop coaster - Th13teen (2010)
- SW7 - Gerstlauer infinity coaster - The Smiler (2013)
- SW8 - GCI wooden coaster - Wicker Man (2018)
For the first time during the development of SW8, the park put out marketing specifically relating to the Secret Weapon programme and for the first time publicly acknowledged all of the coasters involved. They've even put together a video of the programme...