Are we sure Oblivion's Track isn't suffering from Metal fatigue it is 28 years the same age as when Corkscrew left and given it has 7 Shuttles its cycled more timesNot that you should need new parts for a ride that’s just come out of it’s winter maintenance period mind.
- News all the latest
- Theme Park explore the park
- Resort tour the resort
- Future looking forward
- History looking back
- Community and meetups
-
ℹ️ Heads up...
This is a popular topic that is fast moving Guest - before posting, please ensure that you check out the first post in the topic for a quick reminder of guidelines, and importantly a summary of the known facts and information so far. Thanks. - Thread starter Ethan
- Start date
- Favourite Ride
- POTC Disneyland Paris
- Favourite Ride
- Voltron Nevera
You are using an out of date browser. It may not display this or other websites correctly.
You should upgrade or use an alternative browser.
You should upgrade or use an alternative browser.
Ride Availability/Operations 2022-26
DistortAMG
TS Member
Are we sure Oblivion's Track isn't suffering from Metal fatigue it is 28 years the same age as when Corkscrew left and given it has 7 Shuttles its cycled more times
With a lack of any residue signs of ultra sonic testing taking place for more advanced metal fatigue over the winter, I think it can safely be said they are very sure yes.
The highest stress parts of that ride are well supported by the tunnel base, so if there has been testing on this part, we probably couldn't see it.
Besides, track wise, this ride is relatively simple, so even if there was fatigue, it would be much simpler to remedy than say Nemesis, I would think.
Fatigue by its very nature does not apply itself uniformly, so you cannot really compare the maintenance history of one ride as a basis for the current maintenance needs of a completely different ride.
You are correct as the app is showing Sub-Terra, Spinball, Galactica & Thirteen all advertising 11am opening out of the thrill rides.I wouldn’t be surprised if there is an operational distinction between after dark dates and non-after dark dates.
Friday will be the test of that.
They may as well.just close off Katanga Canyon until May. What an absolute disaster of operations, not having Sky ride open yet given all the work on it is embarrassing as wellOblivion has made it onto the ride availability page.:
![]()
Though weirdly, Bugbie-Go-Round still hasn't despite it being closed all year so far.
PhalanaxOperativeA1127
TS Member
They may as well.just close off Katanga Canyon until May. What an absolute disaster of operations, not having Sky ride open yet given all the work on it is embarrassing as well
But then they'd miss out on the pizza & pasta income!
Skyscraper
TS Member
Four now as Smiler has opened, still diabolical though!If you arrived for park opening at 10am today, it looks like an adult visitor had the choice of three rides to choose from, six if you include the Mutiny Bay attractions.
Edit: And that went up to four by 10:30