Sorry to double post however to answer @Bowser questionI believe last time it valleyed, it operated from the press night of Fright Night (3 October) to around the closure period (14-16 October) on one train which was about 10 days.
I understand a huge factor was that it was Fright Night (the park's busiest time of year) so the park didn't want Hyperia down for an extended period so had it on one train to offer minimal disruption (instead of closing the ride for testing for a period of time).
For the first time it valleyed, it tested for about 2 hours before opening on the advertised Golden Day (23 June) on 2 trains. It operated on one train for one day beforehand.
I believe it depends on whether the park are happy to close Hyperia for testing at some point (which might be possible before the Easter Bank Holiday weekend).
I'm seeing on social media that Hyperia is back on 2 trains now.