Dave
TS Founding Member
let’s do an audit.
It’s the 27th of Feb we do have a leap year but we have 63 days until the end of April, in that time….
1) They have to finish the actual track.
2) They have to wire up the various ride systems to the control unit (I am going to assume they have brought the power cable to the ride).
3) Load the trains onto the system.
4) Programme the ride
5) Build the queue
6) Finish building the shed sorry station.
7) install the airgates
8) Run the ride with enough cycles to pass ADIPS
9) Train staff
Genuinely if this ride opens in April then it has been rushed and we had that with the Smiler and I don’t think Merlin nor the UK theme park community want to see that again.
It’s the 27th of Feb we do have a leap year but we have 63 days until the end of April, in that time….
1) They have to finish the actual track.
2) They have to wire up the various ride systems to the control unit (I am going to assume they have brought the power cable to the ride).
3) Load the trains onto the system.
4) Programme the ride
5) Build the queue
6) Finish building the shed sorry station.
7) install the airgates
8) Run the ride with enough cycles to pass ADIPS
9) Train staff
Genuinely if this ride opens in April then it has been rushed and we had that with the Smiler and I don’t think Merlin nor the UK theme park community want to see that again.