Re: Secret Weapon 7 Discussion Continued
I'm afraid I got board of reading the last
few half-dozen pages of discussion. As John has already pointed out there's so much we still don't know about SW7 that trying to compare it to the other major investments is futile, from a complexity point at any rate.
What we can debate over is why this project is so far behind where we expect it to be. Now before I get bombard with messages claiming it isn't behind schedule I thought it was about time I went back to the archives to compare SW7's construction to several other rides. I've chosen to post what I found for Saw (because it should be similar to SW7) and Th13teen (as the last SW).
Important date log: Saw the ride
Information obtained from
Thorpe Park Mania's Saw Mini-site
9th October 2008 < relative time 3 months ago
Track Completion.
3rd November 2008
Station framework complete.
12th December 2008
First known image of the head chopper saw blades in place.
23rd December 2008
First known images of the themed station including the construction of the queue line.
9th January 2009 < relative time present day
First appearance of the ride vehicles.
24th January 2009
Full ride testing. This means that a clearance draw-through must have taken place several weeks before.
Important date log: Th13teen
Information obtained from
Towers Nerd Mini-site
Less is recorded about Th13teen as access to the park was limited (and TT have taken down the most detailed Mini-site) but from what is available:
10th October 2009 < relative time 3 months ago
Track assembly began on-site.
9th November 2009 < relative time 2 months ago
Secret Weapon arrived on-site. If my memory serves me correct all other track pieces had been assembled by this point.
1st February 2010
First picture of the trains. However unlike the first appearance of Saw's trains these were shown on the track which suggests the basic testing had already occurred.
If you wish me to go further back and compare other project timelines I will do so but I can tell you now they are all roughly the same.
SW5Live is a good site to see Air's construction
So baring this in mind I’d say SW7 is fairly significantly behind where it should be. Of course I have no way of knowing what the official schedule is but given that both of the examples I've given were testing through most of January and February in order to open in March you can appreciate why there is a lot of concern that SW7 hasn’t even been built yet.
As for why SW7 is behind the others I’m going to have a guess at the weather. 2012 started off as one of the driest seasons on record but very quickly developed into one of the wettest. That amount of rain water would (as we saw) have delayed the excavation process. This wouldn’t have been such a problem but the rain was pretty relentless. If I remember correctly the 4 Olympic and Paralympic weeks were the only ones this year to be rain free.
Added to the bad weather was the long delay between the planning permission being approved and the start of construction work. I still can’t work out why they didn’t start removing the Black Hole Tent as soon as permission was granted but I’m sure they had their reasons.